Roadwork Schedule: August -September

  • 3 yrs ago

Brooklawn Drive - work will begin on or about August 25. The road will be closed to thru-traffic during milling and paving anticipated for Aug. 31 to Sept. 2.

Naughright Road (beginning south of Fawnridge and extending to Fairview Avenue) - work will begin on or about Sept. 7. The road will be alternating one lane traffic during milling anticipated for Sept. 14 -17 and Sept 21-22. Detours will be in place during paving anticipated for Sept. 23-24.

Long Hill Road (from county line to area of Oxford Lane)- work will begin on or about September 28. The road will be closed to thru-traffic during milling and paving anticipated for Sept. 29-30.

Mission Road milling and paving - late September at a date to be determined.

 